Tract home construction in Ventura County presents a different set of temporary power challenges than a standalone residential build or a commercial project. You are not setting up power for one structure. You are setting up power across an entire development, often before streets are fully in, before permanent utility infrastructure is complete, and on a site where multiple homes are under construction simultaneously. Getting the temporary power layout right from the start affects how efficiently the whole project runs.
On a single home build, one temporary power pole positioned near the utility source is typically sufficient. On a tract home project with ten, twenty, or fifty homes under construction, that single pole does not reach most of the site.
The utility will not span overhead wire more than 100 feet from their source. Any home that is further than that from the utility connection needs its own sub-panel. A multi-set installation solves this: ACO installs a meter pole near the SCE connection point and additional poles at roughly 80-foot intervals across the site, with each lot’s pole carrying a sub-panel that supplies power to that home under construction.
The layout needs to be thought through before installation begins. Where the utility source is located relative to the first and last homes on the tract, which homes are starting first, how the site will phase, and where the job site trailer needs to sit all factor into how the system is designed. This is why ACO recommends a job walk for every multi-set project before equipment is ordered or poles are placed.
Ventura County includes nine incorporated cities, each with its own Building and Safety department, and unincorporated areas handled by the county. A tract home project in Thousand Oaks goes through the City of Thousand Oaks for its building permit and temporary power permit. A project in Camarillo goes through Camarillo. Simi Valley, Moorpark, and Oxnard each have their own processes.
Each city has specific requirements for temporary power inspections. The submittal requirements and inspection checklists are not identical across those jurisdictions, and the unincorporated county areas operate on a different timeline and process than the incorporated cities. ACO’s permit expeditors know the Building and Safety departments in each Ventura County city and handle the application from submission through passed inspection.
ACO’s permit pulling service covers Ventura County in full, including Thousand Oaks, Camarillo, Simi Valley, Moorpark, Oxnard, and unincorporated county areas.
Southern California Edison serves the entirety of Ventura County. There are no municipal utility exceptions. That means the SCE service request and planner process applies to every project in the county. A service planner is assigned to each project and must visit the site to confirm the meter location before ACO can install the pole.
On tract home projects, this meter spot meeting is particularly important. The service planner and the general contractor need to agree on where the primary meter pole goes, which is typically the pole closest to the SCE source that anchors the entire multi-set layout. Getting that location right at the meeting prevents corrections after installation has started.
Like other newer planned communities across Southern California, some developments in Ventura County have underground utility infrastructure. When SCE’s transformer has not yet been installed at a new development, the temporary power connection cannot be completed even if ACO has installed the pole and conduit.
For tract home projects in new Ventura County developments, confirm with SCE that the transformer is set before scheduling the ACO installation. If the transformer is not yet in place, wait. The cost of a second trip because the transformer was not ready is avoidable with a quick SCE status check before mobilizing.
Most tract home projects do not build all homes simultaneously. Construction phases through the development, with some lots starting earlier and others coming online as the project progresses. Temporary power needs to keep pace with that phasing.
ACO can set up the initial poles for the first phase and expand the system as construction phases forward. For projects where the phasing plan is known in advance, building that expansion into the original system design is more cost-effective than adding on pole by pole as the project moves. Discussing the phasing schedule with ACO at the job walk allows the system to be designed for the whole project rather than just the first phase.
The general contractor’s job site office trailer on a tract home project typically needs power from day one. ACO’s trailer connection service connects the trailer directly to the temporary power system, covering HVAC, lighting, and office equipment throughout the project. For multi-set installations, the trailer connection is factored into the system layout rather than treated as a separate add-on.
ACO has been handling temporary power for construction projects across Ventura County for over 35 years. We cover Thousand Oaks, Camarillo, Simi Valley, Moorpark, Oxnard, and surrounding areas, including remote and hard-to-reach locations that other providers will not service.
If you have a tract home project in Ventura County and want to talk through the temporary power layout, call us at (818) 255-3560 or request a free estimate online. Our team will walk the site, design the system, and handle everything from permit to power.